GCL cut-off wall at Huoshan MSW landfill closure project

views:14

The state-of-the-art cut-off wall technology, GCL vertical barrier system was applied at Huoshan MSW landfill closure project so as to better control the contaminant lateral migration, prevent groundwater from polluting. The construction was carried out by Tianjin Zhongliangelin, duration 2021.09.05-2021.10.07. The condtruction team adjusted construction machine and optimized construction schedule to cope with the site special soil condition(weathered rock) and the narrow working space. Job was completed on time according to contract with owner.